Construction of the FHL Tower in Suva has resumed after Fijian Holdings Limited (FHL) secured the necessary regulatory approvals and replacement materials following a prolonged delay.
The project had faced multiple setbacks, including a stop-work order due to regulatory concerns. However, the order was lifted after authorities confirmed that the site complies with Occupational Health and Safety (OHS) standards and all relevant building codes.
In a statement, FHL said it had implemented all recommended safety measures to ensure a secure working environment for employees and contractors.
Work also resumed after Energy Fiji Limited (EFL) granted the site’s electrical installations clearance. EFL confirmed that the project met utility interface protocols and load distribution requirements, with temporary power restored to allow uninterrupted construction.
“With materials secured and statutory approvals in place, efforts are now focused on completing the project while upholding all safety and regulatory requirements,” the company stated. FHL added that it continues to work closely with the main contractor and relevant authorities to maintain steady progress.
The high-rise at the corner of Gordon Street and Thurston Street was originally scheduled for completion in 2022 at a total cost of FJ$67 million. However, the project has experienced delays, including a serious workplace incident in November last year in which two workers were injured.
One of the injured workers reportedly passed away a month later. Following the accident, FHL postponed the tower’s opening, which had been planned for the end of 2024.
While a new completion date has not been confirmed, FHL reaffirmed its commitment to delivering a landmark development that reflects the aspirations of shareholders, stakeholders, tenants, and the wider community.
Related Articles